The off channel
impoundment and the diversion provide 100 year flood protection
for Warren and a reduction in flood flows for all reaches downstream
of the off channel floodwater storage structure.
With the occurrence
of a 100 year flood the off channel impoundment would store an estimated
6,700 acre-feet of water from a drainage area of about 57 square
miles, thus reducing the flow at Warren by approximately 1,400 cubic
feet per second.
Construction was completed
in the summer of 2006.